Canadian Shipping

Canada's National Shipbuilding Strategy Explained

The National Shipbuilding Strategy (NSS) is a federal program under which Canadian shipyards build large vessels for the Royal Canadian Navy and the Canadian Coast Guard. It was formerly called the National Shipbuilding Procurement Strategy (NSPS) and is run by the department of Public Works and Government Services, now known as Public Services and Procurement Canada. The strategy was developed under the government of Prime Minister Stephen Harper as a way to renew the national fleets through long-term, planned work at selected yards instead of one-off contracts.

This page describes how the national shipbuilding strategy began, how its work was divided into packages, which yards took part, what vessels are built under it and what public reports say about its costs. It is a neutral summary of published sources and does not assess the policy. The broader context is covered in the page on the Canadian shipbuilding industry, and the vessels that the strategy delivers to the civilian fleet are described in the guide to the Canadian Coast Guard fleet.

Launch of the national shipbuilding strategy in 2010 and 2011

The strategy was launched on 3 June 2010. Public Works and Government Services issued a solicitation of interest and qualification on 20 September 2010 and closed it on 8 October 2010. Five Canadian shipyards were short-listed for the large vessels:

Between October 2010 and January 2011 the short-listed yards were consulted on the request for proposals, the umbrella agreements, the schedule and the evaluation method. The request for proposals was released on 7 February 2011 and closed on 21 July 2011. Five proposals came from three bidders: Irving Shipbuilding, Seaspan Marine Corp. (the new name of Washington Marine Group from 2011) and Davie Yards. Two proposals were for the combat work package and three were for the non-combat package.

An evaluation organization of Canadian Forces and Coast Guard personnel, together with public servants from Public Works and Government Services, Industry Canada, National Defence and Fisheries and Oceans Canada, assessed the bids. An independent fairness monitor oversaw the process, and the yards were scored on a combination of mandatory and rated requirements. During the final evaluation Davie Yards underwent a corporate restructuring, accepted by the strategy governance on 27 July 2011.

The results for the two larger packages were made public on 19 October 2011. The government selected Irving Shipbuilding for the combat package, valued at about 25 billion dollars at the time, and Seaspan Marine for the non-combat package, valued at about 8 billion dollars. In 2012 the two companies negotiated the contracts for the first project in each package.

Combat and non-combat packages

The strategy was built around separate packages of work, and the yards that won the two larger packages were not permitted to bid on the smaller vessel package. The packages were:

The two large packages were first valued at about 38 billion dollars together. In the latest encyclopedia summary the planned spending is described as exceeding 100 billion dollars, a change linked to project cost increases and to the expansion of the work lists.

Combat package and Irving Shipbuilding

The combat package went to Irving Shipbuilding, whose main facility is the Halifax Shipyard. The company was formed in 1994 when Saint John Shipbuilding bought the yard, and it also owns Woodside Industries and other facilities in Dartmouth, Nova Scotia. The package was originally worth about 30 billion dollars and later grew to more than 80 billion. It covers 21 combatant vessels for the navy and two non-combat vessels for the Coast Guard:

In 2012 Irving Shipbuilding received a 300 million dollar loan from the Nova Scotia government for modernization of the Halifax Shipyard so that it could build vessels for the federal government. The strategy also carries a value proposition requirement, under which the contracted yard reinvests a portion of its contract revenue. Examples from 2016 and 2017 include funding for Arctic research projects in Nunavut and a contribution to the Centre for Ocean Ventures and Entrepreneurship in Nova Scotia.

Non-combat package and Seaspan

The non-combat package was first awarded solely to Seaspan Shipbuilding, with an original value of about 26 billion dollars for seven vessels. It was later expanded to cover up to 30 vessels, with up to 23 built by Seaspan and seven by Davie. Its main projects are:

Seaspan's yard in North Vancouver had to be upgraded to take the work, and the upgrade was completed in November 2014. The first ship built under the strategy, the Offshore Fisheries Science Vessel CCGS Sir John Franklin, was launched there on 8 December 2017. The three fisheries science vessels, Sir John Franklin, Capt. Jacques Cartier and John Cabot, are in service, as is the oceanographic vessel Naalak Nappaaluk, according to the status reported as of May 2026.

NSS strategic partners and umbrella agreements

The yards chosen under the strategy are known as strategic partners of the government, and each is covered by an umbrella agreement with the federal government. Individual contracts for each class of vessel follow under these agreements. The 2023 amendment to the Irving contract is a documented example of how the terms change over time. On 8 August 2023 the federal government announced an amended definition contract with Irving Shipbuilding and an infrastructure investment of 463 million dollars to build the Canadian Surface Combatants. Reports on the amendment note that the original strategic partnership agreement had stated that the company would pay for facility upgrades from its own funds.

The structure rests on three features reported in the sources: a limited number of long-term partner yards, work grouped into large packages, and linked requirements for economic benefit in Canada. The page on Canadian fleet renewal and cabotage explains how the domestic build theme also fits within the wider rules for vessels used in Canadian waters.

Chantier Davie and the third NSS shipyard

In 2019 the Government of Canada decided to run a competition to add a third yard to the strategy. The new yard was expected to specialize in medium and possibly polar icebreakers for the Coast Guard. In December 2019 it was announced that only Davie Yards (now operating as Chantier Davie) had qualified for the icebreaker work. The next step was an umbrella agreement between the government and Davie, expected by the end of 2020, that would formally add the yard under the strategy.

Progress on the agreement was slow. In May 2021 the government said it was expected in late 2021, and that pending its conclusion Davie would build one polar icebreaker while Seaspan built the other. In June 2022 the government again said that negotiations had been started to conclude an agreement by the end of the year. The agreement to incorporate Davie as a third shipyard within the strategy was finally signed in April 2023.

Canadian Surface Combatant and the River-class destroyer

The Canadian Surface Combatant project, now called the River-class destroyer project, is the largest procurement under the strategy. It is meant to replace the Iroquois-class destroyers and the Halifax-class frigates. The four Iroquois-class ships have all been decommissioned, the last being HMCS Athabaskan in March 2017, and the Halifax class is projected to reach the end of its service life in the 2020s.

The project history set out in the sources runs as follows:

The ships are planned at about 8,000 tonnes, almost twice the displacement of the Halifax-class frigates, with wide-area air defence, anti-submarine and anti-ship capabilities. Up to 15 ships are planned, with deliveries starting in the early 2030s. As of 2026, early construction of the first three ships is reported to be under way, and the lead ship, HMCS Fraser, is reported as under construction as of May 2026.

Arctic and Offshore Patrol Ships

The Arctic and Offshore Patrol Ship project began before the strategy. In 2007 the federal government announced plans to acquire six to eight icebreaking warships, and in 2010 the project was grouped with other procurement projects for the navy and the Coast Guard into the strategy. The ships are Polar Class 5 vessels modelled on the Norwegian Coast Guard ship Svalbard, which means they can break limited ice.

Construction of the lead ship, Harry DeWolf, started at the Halifax Shipyard in September 2015. The ship was launched on 15 September 2018. At 103 metres and 6,615 tonnes it was described as the largest Royal Canadian Navy ship built in Canada in 50 years, and it was delivered on 31 July 2020. The class names and launches reported in the sources are:

The first five were in service and the sixth had been delivered as of May 2026. On 22 May 2019 the government announced the process to build two further vessels of the class for the Canadian Coast Guard, bringing the total to eight. The first of these, CCGS Donjek, was launched in 2026, and the second, Sermilik, is under construction. The patrol ships operate in northern waters of the kind described in the page on Arctic shipping in Canada.

Coast Guard vessels under the strategy

The Canadian Coast Guard is a civilian organization with a fleet that includes icebreakers, search and rescue vessels and science ships. Its history shows long cycles of fleet renewal: a period of expansion from the 1960s to the 1980s, cuts in the 1990s, and in 2005 designation as a special operating agency within Fisheries and Oceans Canada. By the first decade of the 21st century plans were announced for nine Mid Shore Patrol Vessels, a polar-class icebreaker later named CCGS Arpatuuq, fisheries science vessels and a new oceanographic research vessel.

The mid-shore patrol vessels were ordered in September 2009 from Irving Shipbuilding, before the strategy was announced in its present form. They cost 194 million dollars for nine ships and were delivered between 2012 and 2014. In 2018 the Coast Guard also confirmed the purchase and retrofit of three large icebreaking anchor-handling tugs, Tor Viking, Balder Viking and Vidar Viking, as an interim measure alongside the new builds.

Under the strategy the Coast Guard receives these classes:

The sources list both polar icebreakers, Arpatuuq and Imnaryuaq, as under construction as of May 2026. Winter operation of icebreakers on inland waters is described separately in the page on icebreaking and winter navigation on the Great Lakes.

Small vessel procurement

The strategy has a separate stream for smaller vessels. Yards that won a large package could not bid for it, which left the work to other Canadian shipyards. Contracts under it are announced as they are awarded rather than as one package. The sources used here do not give a single list or value for this stream, so this page does not quantify it.

Project costs, reviews and reported changes

Cost growth is a recurring subject in published summaries of the program, and the sources report the following changes without drawing conclusions:

For the surface combatant project, the Parliamentary Budget Officer estimated in 2021 the cost of 15 Type 26 ships at 77.3 billion dollars, rising to 79.7 billion dollars with a one-year delay in the start of construction and 82.1 billion with a two-year delay. The reported cost of the first six patrol ships rose by 810 million dollars by 2018 and by a further 780 million in 2023, and that of the two Coast Guard variants rose by 100 million. Reports on the strategy by the Auditor General of Canada are not summarized here because they could not be verified from an official source.

Procurement framework and schedule

Taken together, the sources describe a procurement framework with these elements:

Order changes affect delivery dates, and the Coast Guard fleet depends on the schedule. The related page on the history of Canadian shipping shows earlier shipbuilding programs, and the Canadian marine industry's economic impact gives context on jobs and output. Training for the crews who operate the new vessels is covered in the page on Canadian seafarers training and certification. The two main partner yards are located in port cities described in the pages on the Port of Halifax and the Port of Vancouver.

Frequently asked questions

When was the National Shipbuilding Strategy launched?

It was launched on 3 June 2010, and the winning yards for the combat and non-combat packages were announced on 19 October 2011.

Which shipyards take part in the strategy?

Irving Shipbuilding in Halifax holds the combat package, Seaspan in North Vancouver holds the non-combat package, and Davie in Lévis, Quebec, was added as a third yard through an agreement signed in April 2023.

What is the difference between the combat and non-combat packages?

The combat package covers warships such as the Arctic and Offshore Patrol Ships and the River-class destroyers, plus two Coast Guard variants. The non-combat package covers auxiliary ships, science vessels and icebreakers.

What is the Canadian Surface Combatant?

It is the project to replace the Iroquois-class and Halifax-class warships with up to 15 River-class destroyers based on the Type 26 design, built by Irving Shipbuilding under a contract signed on 8 February 2019.

Which Coast Guard ships are built under the strategy?

The list includes the three Offshore Fisheries Science Vessels, the Offshore Oceanographic Science Vessel, two polar icebreakers, Multi-Purpose Icebreakers, Program Icebreakers and two variants of the Harry DeWolf class.

Last updated 2026-11-18

Sources

  1. Wikipedia, National Shipbuilding Strategy: https://en.wikipedia.org/wiki/National_Shipbuilding_Strategy
  2. Wikipedia, River-class destroyer (2030s): https://en.wikipedia.org/wiki/River-class_destroyer_(2030s)
  3. Wikipedia, Harry DeWolf-class offshore patrol vessel: https://en.wikipedia.org/wiki/Harry_DeWolf-class_offshore_patrol_vessel
  4. Wikipedia, Irving Shipbuilding: https://en.wikipedia.org/wiki/Irving_Shipbuilding
  5. Wikipedia, Canadian Coast Guard: https://en.wikipedia.org/wiki/Canadian_Coast_Guard